Skip to Main Content


This information is provided free of charge by the Department of Industrial Relations from its web site at www.dir.ca.gov. These regulations are for the convenience of the user and no representation or warranty is made that the information is current or accurate. See full disclaimer at https://www.dir.ca.gov/od_pub/disclaimer.html.
 
Subchapter 4. Construction Safety Orders
Article 29. Erection and Construction
Return to index
New query

Appendix C to Section 1710 -- Guidelines for Establishing the Components of a Site-Specific Erection Plan: Non-Mandatory Guidelines for Complying with Section 1710(c)(5)


(a) General. This appendix serves as a guideline to assist employers who elect to develop a site-specific erection plan in accordance with Section 1710(c)(5) with alternate means and methods to provide employee protection in accordance with Sections 1710(c)(5), 1710(d)(9), 1710(h)(1)(C) or Section 1710(h)(5)(D).


NOTE: The development of a site-specific erection plan does not eliminate the mandatory requirement for an erection plan and procedure prepared by a civil engineer as required by Section 1709(d) when trusses or beams over 25 feet long are used.

(b) Development of a site-specific erection plan. Pre-construction conference(s) and site inspection(s) are held between the erector and the controlling contractor, and others such as the project engineer and fabricator before the start of steel erection. The purpose of such conference(s) is to develop and review the site-specific erection plan that will meet the requirements of this section.

(c) Components of a site-specific erection plan. In developing a site-specific erection plan, a steel erector considers the following elements:

(1) The sequence of erection activity, developed in coordination with the controlling contractor, that includes the following:

(A) Material deliveries:

(B) Material staging and storage; and

(C) Coordination with other trades and construction activities.

(2) A description of the crane and derrick selection and placement procedures, including the following:

(A) Site preparation;

(B) Path for overhead loads; and

(C) Critical lifts, including rigging supplies and equipment.

(3) A description of steel erection activities and procedures, including the following:

(A) Stability considerations requiring temporary bracing and guying;

(B) Erection bridging terminus point;

(C) Anchor rod (anchor bolt) notifications regarding repair, replacement and modifications;

(D) Columns and beams (including joists and purlins);

(E) Connections;

(F) Decking; and

(G) Ornamental and miscellaneous iron.

(4) A description of the fall protection procedures that will be used to comply with Section 1710(m).

(5) A description of the procedures that will be used to comply with Section 1710(j).

(6) A description of the special procedures required for hazardous non-routine tasks.

(7) A certification for each employee who has received training for performing steel erection operations as required by Section 1710(q).

(8) A list of the qualified and competent persons.

(9) A description of the procedures that will be utilized in the event of rescue or emergency response.

(d) Other plan information. The plan:

(1) Includes the identification of the site and project; and

(2) Is signed and dated by the qualified person(s) responsible for its preparation and modification.

NOTE

Authority cited: Section 142.3, Labor Code. Reference: Section 142.3, Labor Code


Go BackGo Back to Article 29 Table of Contents