| This information is provided free of charge by the Department of Industrial Relations from its web site at www.dir.ca.gov. These regulations are for the convenience of the user and no representation or warranty is made that the information is current or accurate. See full disclaimer at http://www.dir.ca.gov/od_pub/disclaimer.html. |
| New query |
| Exception: This section does not cover electrical transmission towers, communication and broadcast towers, or tanks. |
| NOTE: Additional requirements for work on steel framed structures are contained in Article 20, Section 1635(b) of these orders. |
| (3) The duties of controlling contractors under this section include the duties specified in (c)(1) & (3), (f)(2)(B), (j)(2) and (o) of this section. |
| (B) Any repairs, replacements and modifications to the anchor bolts were conducted in accordance with Section 1710(f)(2). |
| (3) Site layout. The controlling contractor shall ensure that the following is provided and maintained: |
| Exception: This requirement does not apply to roads outside of the construction site. |
| (4) Pre-planning of overhead hoisting operations. All hoisting operations in steel erection shall be pre-planned to ensure that the requirements of Section 1710(d)(1) are met. |
| (1) Working under loads. |
| (A) Routes for suspended loads shall be pre-planned to ensure that no employee is working below a suspended load except as necessary for: |
| 1. Connectors making the initial connection of the steel; or |
| 2. Riggers when hooking or unhooking of the load. |
| (B) When working under suspended loads, the following criteria shall be met: |
| 1. Materials being hoisted shall be rigged to prevent unintentional displacement; |
| 2. Hooks with self-closing safety latches or their equivalent shall be used to prevent components from slipping out of the hook; and |
| 3. All loads shall be rigged by a qualified rigger. |
| (2) Multiple Lift Rigging Procedure. |
| (A) A multiple lift shall only be performed if the following criteria are met: |
| 1. A multiple lift rigging assembly is used; |
| 2. A maximum of five members are hoisted per lift; |
| 3. Rigging procedures shall prevent hazardous contact between the structural steel members being hoisted and adjacent structures or workers; |
| 4. Only beams and similar structural members are lifted; |
| 5. All employees engaged in the multiple lift have been trained in these procedures in accordance with Section 1710(q)(3)(A); and |
| 6. No crane is permitted to be used for a multiple lift where such use is contrary to the manufacturer's specifications and limitations. |
| (C) The total load shall not exceed: |
| 1. 75 percent of the rated capacity of the hoisting equipment specified in the hoisting equipment load charts; |
| 2. The rigging capacity specified by the manufacturer. |
| (D) The multiple lift rigging assembly shall be rigged with members: |
| 1. Attached at their center of gravity and maintained reasonably level; |
| 2. Rigged from top down; and |
| 3. Rigged at least 7 feet (2.1 m) apart. |
| (E) The members on the multiple lift rigging assembly shall be set from the bottom up. |
| (F) Controlled load lowering shall be used whenever the load is over the connectors. |
| (3) Whenever there is any doubt as to safety, the crane or derrick operator shall have the authority to stop and refuse to handle loads until safety has been assured. |
| (4) Metal decking bundles shall be landed on framing members so that enough support is provided to allow the bundles to be unbanded without dislodging the bundles from the supports. |
| (5) Temporary loads placed on a derrick floor shall be distributed over the underlying support members so as to prevent local overloading of the deck material. |
| (6) Bundle packaging and strapping shall not be used for hoisting unless specifically designed for that purpose. |
| (7) If loose items such as dunnage, flashing, or other materials are placed on the top of metal decking bundles to be hoisted, such items shall be secured to the bundles. |
| (9) Safety latches on hooks shall not be deactivated or made inoperable except: |
| (A) When a qualified rigger has determined that the hoisting and placing of purlins and single joists can be performed more safely by doing so; and |
| (B) When the steel erector develops and implements a site-specific erection plan that ensures the load will not travel over or expose employees in other trades to the hazards of suspended loads. |
| (1) Shear connectors and other similar devices. |
| NOTE: Section 1710(n)(8) prohibits the installation of shear connectors within a controlled decking zone. |
| (1) General requirements for erection stability. |
| (A) All columns shall be anchored by a minimum of 4 anchor rods (anchor bolts). |
| Exception: When columns are braced or guyed to provide the stability to support an eccentric load as specified in subsection (f)(1)(B) of this section. |
| (C) Columns shall be set on level finished floors, pre-grouted leveling plates, leveling nuts, or shim packs which are adequate to transfer the construction loads. |
| (D) All columns shall be evaluated by a competent person to determine whether guying or bracing is needed; if guying or bracing is needed, it shall be installed. |
| (2) Repair, replacement or field modification of anchor rods (anchor bolts). |
| (A) Anchor rods (anchor bolts) shall not be repaired, replaced or field-modified without the approval of the project structural engineer of record. |
| NOTE: Minor adjustment of anchor rods (anchor bolts) that do not affect the structural integrity of anchor rods (anchor bolts) are not considered "repairs" for the purposes of this subsection. |
| (2) A competent person shall determine if more than two bolts are necessary to ensure the stability of cantilevered members; if additional bolts are needed, they shall be installed. |
| (4) Double connections at columns and/or at beam webs over a column. |
| (6) Perimeter columns. Perimeter columns shall not be erected unless: |
| (1) General. |
| 2. The bottom chords of steel joists at columns shall be stabilized to prevent rotation during erection. |
| 3. Hoisting cables shall not be released until the seat at each end of the steel joist is field-bolted, and each end of the bottom chord is restrained by the column stabilizer plate. |
| (B) Where constructibility does not allow a steel joist to be installed at the column: |
| 1. An alternate means of stabilizing joists shall be installed on both sides near the column and shall: |
| a. Provide stability equivalent to subsection (h)(1)(A) of this section; |
| b. be designed by a qualified person; |
| c. be shop installed; and |
| d. be included in the erection drawings. |
| 2. Hoisting cables shall not be released until the seat at each end of the steel joist is field-bolted and the joist is stabilized. |
| (D) A steel joist or steel joist girder shall not be placed on any support structure unless such structure is stabilized. |
| (E) When steel joist(s) are landed on a structure, they shall be secured to prevent unintentional displacement prior to installation. |
| (F) No modification that affects the strength of a steel joist or steel joist girder shall be made without the approval of the project structural engineer of record. |
| (G) Field-bolted joists. |
| 2. These connections shall be field-bolted unless constructibility does not allow. |
| (H) Steel joists and steel joist girders shall not be used as anchorage points for a fall arrest system unless written approval to do so is obtained from a qualified person. |
| (I) A bridging terminus point shall be established before bridging is installed. (See Appendix A of this section.) |
| (2) Attachment of steel joists and steel joist girders. |
| (D) Panels that have been pre-assembled from steel joists with bridging shall be attached to the structure at each corner before the hoisting cables are released. |
| (3) Erection of steel joists. |
| (A) Both sides of the seat of one end of each steel joist that requires bridging under Tables A and B shall be attached to the support structure before hoisting cables are released. |
| (C) On steel joists that do not require erection bridging under Tables A and B, only one employee shall be allowed on the joist until all bridging is installed and anchored. |
| (E) When permanent bridging terminus points cannot be used during erection, additional temporary bridging terminus points are required to provide stability. (See Appendix A of this section.) |
| (4) Erection bridging. |
| (A) Where the span of the steel joist is equal to or greater than the span shown in Tables A and B, the following shall apply: |
| 1. A row of bolted diagonal erection bridging shall be installed near the midspan of the steel joist; |
| 2. Hoisting cables shall not be released until this bolted diagonal erection bridging is installed and anchored; and |
| 3. No more than one employee shall be allowed on these spans until all other bridging is installed and anchored. |
| (B) Where the span of the steel joist is over 60 feet (18.3 m) through 100 feet (30.5 m), the following shall apply: |
| 1. All rows of bridging shall be bolted diagonal bridging; |
| 2. Two rows of bolted diagonal erection bridging shall be installed near the third points of the steel joist; |
| 3. Hoisting cables shall not be released until this bolted diagonal erection bridging is installed and anchored; and |
| 4. No more than two employees shall be allowed on these spans until all other bridging is installed and anchored. |
| (C) Where the span of the steel joist is over 100 feet (30.5 m) through 144 feet (43.9 m), the following shall apply: |
| 1. All rows of bridging shall be bolted diagonal bridging; |
| 2. Hoisting cables shall not be released until all bridging is installed and anchored; and |
| 3. No more than two employees shall be allowed on these spans until all bridging is installed and anchored. |
| (D) For steel members spanning over 144 feet (43.9 m), the erection methods used shall be in accordance with subsection (g) of this section. |
| (F) When bolted diagonal erection bridging is required by this section, the following shall apply: |
| 1. The bridging shall be indicated on the erection drawing; |
| 2. The erection drawing shall be the exclusive indicator of the proper placement of this bridging; |
| 3. Shop-installed bridging clips, or functional equivalents, shall be used where the bridging bolts to the steel joists; |
| 5. Bridging attachments shall not protrude above the top chord of the steel joist. |
| (5) Landing and placing loads. |
| (A) During the construction period, the employer placing a load on steel joists shall ensure that the load is distributed so as not to exceed the carrying capacity of any steel joist. |
| (B) Except for subsection (h)(5)(D) of this section, no construction loads are allowed on the steel joists until all bridging is installed and anchored and all joist-bearing ends are attached. |
| (D) No bundle of decking may be placed on steel joists until all bridging has been installed and anchored and all joist bearing ends attached, unless all of the following conditions are met: |
| 1. The employer has first determined from a qualified person and documented in a site-specific erection plan that the structure or portion of the structure is capable of supporting the load; |
| 2. The bundle of decking is placed on a minimum of three steel joists; |
| 3. The joists supporting the bundle of decking are attached at both ends; |
| 4. At least one row of bridging is installed and anchored; |
| 5. The total weight of the bundle of decking does not exceed 4,000 pounds (1816 kg); and |
| 6. The edge of the construction load shall be placed within 1 foot (.30 m) of the bearing surface of the joist end. |
| (1) All of the requirements of this section apply to the erection of systems-engineered metal buildings except subsection (f) (column anchorage) and subsection (h) (open web steel joists). |
| (2) Each structural column shall be anchored by a minimum of four anchor rods (anchor bolts). |
| (4) Construction loads shall not be placed on any structural steel framework unless such framework is safely bolted, welded or otherwise adequately secured. |
| (6) Both ends of all steel joists or cold-formed joists shall be fully bolted and/or welded to the support structure before: |
| (A) Releasing the hoisting cables; |
| (B) Allowing an employee on the joists; or |
| (C) Allowing any construction loads on the joists. |
| (7) Purlins may only be used as a walking/working surface when installing safety systems, after all permanent bridging has been installed and fall protection is provided. |
| (8) Construction loads may be placed only within a zone that is within 8 feet (2.5 m) of the center-line of the primary support member. |
| (1) Securing loose items aloft. All materials, equipment, and tools, which are not in use while aloft, shall be secured against accidental displacement. |
| Note: If the periphery fall protection is intended to be used as a catenary line, it shall meet the provisions of Section 1710(m)(4). |
| (4) Midrail protection. |
| (A) Midrail protection shall be installed as soon as the metal decking has been installed; and |
| (B) Shall be installed prior to the decked area being used by trades other than the steel erector or decking crew. |
| (5) Framed metal deck openings shall have structural members turned down to allow continuous deck installation except where not allowed by structural design constraints or constructibility. |
| Note: Where a planked floor is not practical, subsection (l)(2) of this section applies. |
| (1) Connecting. |
| NOTE: For fall protection requirements associated with work above reinforcing steel and similar projections, see Section 1712 of the Construction Safety Orders. |
| (C) Shinning of Columns. |
| (2) Work Other Than Connecting. |
| When performing any other work at a work point, iron workers shall be provided with and use personal fall protection as described in Article 24 where the fall distance is greater than 15 feet. |
| (3) Traveling at Periphery or Interior of Building. |
| (A) When moving from work point to work point or releasing slings, and the fall distance is greater than 30 feet or two stories, whichever is less, connectors: |
| 1. Shall coon or walk the bottom flange (inside flange of peripheral beams); |
| 2. May walk the top surface of securely landed decking bundles; or |
| 3. May walk the top flange if they are tied-off to catenary lines or use other fall protection in accordance with Article 24. |
| (B) When moving from work point to work point or releasing slings, and the fall distance is greater than 15 feet for other than connecting, iron workers: |
| 1. Shall coon or walk the bottom flange (inside flange of peripheral beams); |
| 2. May walk the top surface of securely landed decking bundles; or |
| 3. May walk the top flange if they are tied-off to catenary lines or use other fall protection in accordance with Article 24. |
| (4) Pendant lines, catenary lines and other lines used to secure workers shall be used in accordance with the Construction Safety Orders, Section 1670. |
| (2) The CDZ shall be limited to that area where metal decking is initially being installed and forms the leading edge work. |
| (3) The implementation of a CDZ shall be under the supervision of a competent person. |
| (A) The name or other method of identification for each employee (e.g., job title) who is designated to work in the CDZ must be documented. |
| (B) The documentation required by this subsection shall be in writing and shall be available at the job site. |
| (A) The safety monitor shall be competent to recognize fall hazards; |
| (B) The safety monitor shall warn the employee when it appears that the employee is unaware of a fall hazard or is acting in an unsafe manner; |
| (C) The safety monitor shall be within visual sighting distance of the employee; |
| (D) The safety monitor shall be close enough to communicate orally with the employee; |
| (E) The safety monitor shall not have other responsibilities which could take the monitor's attention from the monitoring function; and |
| (F) The safety monitor shall not be located within the CDZ. |
| (6) In each CDZ, the following shall apply: |
| (A) Each employee working within a CDZ shall be protected from fall hazards greater than two stories or 30 feet, whichever is less, by the use of a personal fall protection system. |
| (B) Access to a CDZ shall be limited to only those employees engaged in leading edge work. |
| (C) The boundaries of a CDZ shall be designated and clearly marked. The CDZ shall be defined by a control line or by any equivalent means that restrict access. |
| 1. Control lines shall meet the requirements of Section 1671.2(a)(4) through (a)(6). |
| 2. When control lines or equivalent means are used, they shall be erected not less than 6 feet from the unprotected leading edge. |
| 3. The CDZ shall not be more than 90 feet wide and 90 feet deep from any leading edge. |
| 4. Signs meeting the requirements of the General Industry Safety Orders, Section 3340 shall be posted to warn unauthorized persons to stay out of the CDZ. |
| (8) Final deck attachments, installation of shear connectors, and flashing shall not be performed in the CDZ. |
| (9) Where a CDZ is being used, the employer shall assure that each affected employee has been provided training in accordance with subsection (q)(3)(C) of this section. |
| (1) Has directed the steel erector to leave the wire rope or other guardrail protection in place; and |
| (2) Has inspected and accepted control and responsibility of the wire rope or other guardrail protection prior to authorizing persons other than steel erectors to work in the area. |
| (1) Training personnel. Training required by this section shall be provided by a qualified person(s). |
| (2) Fall hazard training. The employer shall provide a training program for all employees exposed to fall hazards. The program shall include training and instruction in the following areas: |
| (A) The recognition and identification of fall hazards in the work area; |
| (C) The correct procedures for erecting, maintaining, disassembling, and inspecting the fall protection systems to be used; |
| (D) The procedures to be followed to prevent falls to lower levels and through or into holes and openings in walking/working surfaces and walls; and |
| (E) The fall protection requirements for structural steel erection. |
| 1. The proper inspection and removal of hoisting slings, eye-hooks and other rigging components used in multiple lift rigging. |
| 2. Procedures for determining the proper sling length for structural members. |
| 3. The use of rated load charts and capacities for manufactured rigging equipment. |
| 4. The design and use of manufactured rigging assemblies. |
| 5. Proper rigging techniques to maintain a distance of 7 feet between structural members being hoisted. |
| 6. Instruction that no more than 5 structural members can be hoisted per lift. |
| 7. Proper techniques for rigging structural members from the top down and setting structural members from the bottom up. |
| 8. Procedures and techniques for rigging structural members at the center of gravity. |
| 9. Procedures to ensure that no crane is used for multiple lifts that violates the crane manufacturer's specifications. |
| 10. Procedures to ensure that no load exceeds 75 percent of the rated capacity for the hoisting equipment as specified in the hoisting equipment load charts. |
| 11. The use of controlled load lowering on hoisting equipment used for multiple lifts. |
| 12. Procedures for performing multiple lifts that are site-specific. |
| 13. Procedures for preplanning overhead routes of suspended loads. |
| (B) Connector procedures. The employer shall ensure that each connector has been provided training in the following areas: |
| 1. The nature of the hazards associated with connecting; and |
| 2. Shinning of columns, access, proper connecting techniques and work practices required by subsections (g)(4) and (m) of this section. |
| (C) Controlled Decking Zone Procedures. Where CDZs are being used, the employer shall assure that each employee has been provided training in the following areas: |
| 1. The nature of the hazards associated with work within a controlled decking zone; and |
| 2. The establishment of CDZs, access, proper installation techniques and work practices required by subsection (n) of this section. |
| Note: Authority cited: Section 142.3, Labor Code. Reference: Sections 142.3, 7252, 7253, 7254, 7258, 7261, 7262 and 7266, Labor Code. |
Go
Back to Article 29 Table of Contents