GENERAL PREVAILING WAGE DETERMINATION MADE BY THE DIRECTOR OF INDUSTRIAL RELATIONS PURSUANT TO CALIFORNIA LABOR CODE PART 7, CHAPTER 1, ARTICLE 2, SECTIONS 1770, 1773 AND 1773.1 FOR COMMERCIAL BUILDING, HIGHWAY, HEAVY CONSTRUCTION AND DREDGING PROJECTS

LOCALITY: LAKE COUNTY

DETERMINATION: LAK-2020-2

CRAFT CLASSIFICATION CRAFT FOOTNOTE ISSUE DATE EXPIRATION DATE DATE OF NEXT INCREASE 1 AMOUNT OF INCREASE 1 INCREASE FOOTNOTE 1 DATE OF NEXT INCREASE 2 AMOUNT OF INCREASE 2 INCREASE FOOTNOTE 2 DATE OF NEXT INCREASE 3 AMOUNT OF INCREASE 3 INCREASE FOOTNOTE 3
BRICKLAYER, BLOCKLAYER: BRICKLAYER, BLOCKLAYER, STONEMASON 08/22/2020 04/30/2021** 05/01/2021 $2.850 A
BRICKLAYER, BLOCKLAYER: POINTER, CLEANER, CAULKER, WATERPROOFER 08/22/2020 06/30/2021** 07/01/2021 $2.500 A 07/01/2022 $2.500 A
BRICK TENDER 08/22/2020 06/30/2021** 07/01/2021 $2.450 A 07/01/2022 $2.000 A
CARPET, LINOLEUM, SOFT FLOOR LAYER 02/22/2020 12/31/2020** 01/01/2021 $3.000 A 01/01/2022 $3.000 A
CARPET, LINOLEUM, FLOOR COVERING HANDLER AFTER 3 YEARS 02/22/2020 12/31/2020** 01/01/2021 $1.500 A 01/01/2022 $1.500 A
CARPET, LINOLEUM, FLOOR COVERING HANDLER TRAINEE, FIRST 3 MONTHS 02/22/2020 12/31/2020** 01/01/2021 $0.960 A 01/01/2022 $0.960 A
CARPET, LINOLEUM, FLOOR COVERING HANDLER TRAINEE, SECOND 3 MONTHS 02/22/2020 12/31/2020** 01/01/2021 $1.080 A 01/01/2022 $1.080 A
ELECTRICIAN: COMM & SYSTEM INSTALLER 02/22/2020 11/30/2020** 12/01/2020 $2.820 A 12/01/2021 $2.770 A
ELECTRICIAN: COMM & SYSTEM TECH. 02/22/2020 11/30/2020** 12/01/2020 $2.820 A 12/01/2021 $2.770 A
MARBLE FINISHER B 08/22/2020 07/31/2021** 08/01/2021 $1.750 A 08/01/2022 $2.150 A 08/01/2023 $2.250 A
MARBLE MASON B 08/22/2020 07/31/2021** 08/01/2021 $2.500 A 08/01/2022 $3.250 A 08/01/2023 $3.500 A
PAINTER: TAPER 02/22/2020 12/31/2020** 01/01/2021 $2.750 A 07/01/2021 $2.750 A
PLASTER TENDER 08/22/2020 06/30/2021** 07/01/2021 $2.750 A 07/01/2022 $2.750 A
PLUMBER: PLUMBER, STEAMFITTER 08/22/2020 06/30/2021** 07/01/2021 $3.000 A 07/01/2022 $3.000 A
PLUMBER: PLUMBING SERVICE AND REPAIR, LIGHT COMMERCIAL 08/22/2020 06/30/2021** 07/01/2021 $2.550 A 07/01/2022 $2.550 A
PLUMBER: REFRIGERATION FITTER (HVAC) 08/22/2020 06/30/2021** 07/01/2021 $3.000 A 07/01/2022 $3.000 A
PLUMBER: AIR CONDITIONING & REFRIGERATION/HVAC - SERVICE WORK 08/22/2020 06/30/2021** 07/01/2021 $3.000 A 07/01/2022 $3.000 A
PLUMBER: LANDSCAPE/IRRIGATION PIPEFITTER 08/22/2020 06/30/2021** 07/01/2021 $2.550 A 07/01/2022 $2.550 A
PLUMBER: UNDERGROUND/UTILITY PIPEFITTER 08/22/2020 06/30/2021** 07/01/2021 $2.550 A 07/01/2022 $2.550 A
SHEET METAL WORKER 08/22/2020 06/27/2021** 06/28/2021 $3.500 A
SHEET METAL WORKER TOTAL SHEET METAL CONTRACT OF $200000 OR LESS 08/22/2020 06/27/2021** 06/28/2021 $3.000 A
SHEET METAL WORKER SERVICE MECHANIC (TOTAL SHEET METAL CONTRACT OF $200000 OR LESS) 08/22/2020 06/27/2021** 06/28/2021 $2.100 A
SHEET METAL WORKER SERVICE TECHNICIAN (TOTAL SHEET METAL CONTRACT OF $200000 OR LESS) 08/22/2020 06/27/2021** 06/28/2021 $1.930 A
SHEET METAL WORKER AIR CONDITIONING SPECIALIST (TOTAL SHEET METAL CONTRACT OF $200000 OR LESS) 08/22/2020 06/27/2021** 06/28/2021 $1.580 A
SHEET METAL WORKER AIR CONDITIONING JOURNEYMAN (TOTAL SHEET METAL CONTRACT OF $200000 OR LESS) 08/22/2020 06/27/2021** 06/28/2021 $1.930 A
SHEET METAL WORKER METAL DECK & SIDING 08/22/2020 06/30/2021** 07/01/2021 $2.500 A 07/01/2022 $2.700 A
TERRAZZO FINISHER C 08/22/2020 06/30/2021** 07/01/2021 $1.750 A
TERRAZZO WORKER C 08/22/2020 06/30/2021** 07/01/2021 $3.000 A

Return to wage page

FOOTNOTES

**
THE RATE TO BE PAID FOR WORK PERFORMED AFTER THIS DATE HAS BEEN DETERMINED. IF WORK WILL EXTEND PAST THIS DATE, THE NEW RATE MUST BE PAID AND SHOULD BE INCORPORATED IN CONTRACTS ENTERED INTO NOW. CONTACT THE OFFICE OF THE DIRECTOR RESEARCH UNIT FOR SPECIFIC RATES AT (415) 703-4774.
A
THE PREDETERMINED INCREASE SHOWN IS TO BE ALLOCATED TO WAGES AND/OR EMPLOYER PAYMENTS. PLEASE CONTACT THE OFFICE OF THE DIRECTOR - RESEARCH UNIT AT (415) 703-4774 WHEN THE PREDETERMINED INCREASE BECOMES DUE TO CONFIRM THE DISTRIBUTION. PLEASE ALSO EXAMINE THE IMPORTANT NOTICES TO SEE IF ANY MODIFICATIONS HAVE BEEN ISSUED, AS THERE MAY BE REDUCTIONS TO PREDETERMINED INCREASES.
B
EMPLOYEES WORKING ON ANY SUSPENDED PLATFORM/SCAFFFOLD SHALL BE PAID AN ADDITIONAL $20.00 PER DAY ABOVE THE WAGE RATE.
C
THE RATIO OF TERRAZZO FINISHER HOURS TO TERRAZZO WORKER HOURS SHALL NOT EXCEED TWO (2) TO ONE (1).