GENERAL PREVAILING WAGE DETERMINATION MADE BY THE DIRECTOR OF INDUSTRIAL RELATIONS PURSUANT TO CALIFORNIA LABOR CODE PART 7, CHAPTER 1, ARTICLE 2, SECTIONS 1770, 1773 AND 1773.1 FOR COMMERCIAL BUILDING, HIGHWAY, HEAVY CONSTRUCTION AND DREDGING PROJECTS

LOCALITY: MARIN COUNTY

DETERMINATION: MAR-2019-1

CRAFT CLASSIFICATION CRAFT FOOTNOTE ISSUE DATE EXPIRATION DATE DATE OF NEXT INCREASE 1 AMOUNT OF INCREASE 1 INCREASE FOOTNOTE 1 DATE OF NEXT INCREASE 2 AMOUNT OF INCREASE 2 INCREASE FOOTNOTE 2 DATE OF NEXT INCREASE 3 AMOUNT OF INCREASE 3 INCREASE FOOTNOTE 3 DATE OF NEXT INCREASE 4 AMOUNT OF INCREASE 4 INCREASE FOOTNOTE 4 DATE OF NEXT INCREASE 5 AMOUNT OF INCREASE 5 INCREASE FOOTNOTE 5
BRICKLAYER, BLOCKLAYER: POINTER, CLEANER, CAULKER, WATERPROOFER 02/22/2019 06/30/2019** 07/01/2019 $2.500 A 07/01/2020 $2.500 A 07/01/2021 $2.500 A 07/01/2022 $2.500 A
BRICK TENDER 08/22/2018 06/30/2019** 07/01/2019 $1.200 A
ELECTRICIAN: INSIDE WIREMAN 08/22/2018 05/31/2019** 06/01/2019 $3.000 A 06/01/2020 $3.000 A
ELECTRICIAN: CABLE SPLICER 08/22/2018 05/31/2019** 06/01/2019 $3.000 A 06/01/2020 $3.000 A
ELECTRICIAN: TUNNEL WIREMAN 08/22/2018 05/31/2019** 06/01/2019 $3.000 A 06/01/2020 $3.000 A
ELECTRICIAN: TUNNEL CABLE SPLICER 08/22/2018 05/31/2019** 06/01/2018 $3.000 A 06/01/2020 $3.000 A
FIELD SURVEYOR: CHIEF OF PARTY B 02/22/2019 02/29/2020** 03/01/2020 $3.000 A
FIELD SURVEYOR: INSTRUMENTMAN B 02/22/2019 02/29/2020** 03/01/2020 $3.000 A
FIELD SURVEYOR: CHAINMAN/RODMAN B 02/22/2019 02/29/2020** 03/01/2020 $3.000 A
GLAZIER C 02/22/2019 06/30/2019** 07/01/2019 $1.500 A 01/01/2020 $1.500 A 07/01/2020 $1.500 A 01/01/2021 $1.500 A
PAINTER: BRUSH AND SPRAY D 02/22/2019 12/31/2019** 01/01/2020 $2.000 A
PAINTER: METALIZING AND THERMAL SPRAY D 02/22/2019 12/31/2019** 01/01/2020 $3.000 E
PAINTER: INDUSTRIAL PAINTER F 02/22/2019 12/31/2019** 01/01/2020 $2.250 G
PAINTER: SANDBLASTER, STEAM CLEANER, WATERBLASTER D 02/22/2019 12/31/2019** 01/01/2020 $2.000 A
PAINTER: EXOTIC MATERIALS D 02/22/2019 12/31/2019** 01/01/2020 $2.000 A
PAINTER: PAPERHANGER, WALLCOVERING, LEAD ABATEMENT D 02/22/2019 12/31/2019** 01/01/2020 $2.000 A
PAINTER: TAPER 02/22/2019 12/31/2019** 01/01/2020 $2.500 A 01/01/2021 $2.750 A 07/01/2021 $2.750 A
PLASTERER 02/22/2019 06/30/2019** 07/01/2019 $2.750 A 07/01/2020 $2.750 A
PLUMBER: PLUMBER, STEAMFITTER 08/22/2018 06/30/2019** 07/01/2019 $3.000 A 07/01/2020 $3.000 A 07/01/2021 $3.000 A 07/01/2022 $3.000 A
PLUMBER: PLUMBING SERVICE AND REPAIR, LIGHT COMMERCIAL 08/22/2018 06/30/2019** 07/01/2019 $2.550 A 07/01/2020 $2.550 A 07/01/2021 $2.550 A 07/01/2022 $2.550 A
PLUMBER: REFRIGERATION FITTER (HVAC) 08/22/2018 06/30/2019** 07/01/2019 $3.000 A 07/01/2020 $3.000 A 07/01/2021 $3.000 A 07/01/2022 $3.000 A
PLUMBER: AIR CONDITIONING & REFRIGERATION/HVAC - SERVICE WORK 08/22/2018 06/30/2019** 07/01/2019 $3.000 A 07/01/2020 $3.000 A 07/01/2021 $3.000 A 07/01/2022 $3.000 A
PLUMBER: LANDSCAPE/IRRIGATION PIPEFITTER 08/22/2018 06/30/2019** 07/01/2019 $2.550 A 07/01/2020 $2.550 A 07/01/2021 $2.550 A 07/01/2022 $2.550 A
PLUMBER: UNDERGROUND/UTILITY PIPEFITTER 08/22/2018 06/30/2019** 07/01/2019 $2.550 A 07/01/2020 $2.550 A 07/01/2021 $2.550 A 07/01/2022 $2.550 A
PLUMBER: SPRINKLER FITTER (FIRE PROTECTION AND FIRE CONTROL SYSTEMS) 02/22/2019 07/28/2019** 07/29/2019 $3.500 A 08/03/2020 $3.500 A 08/02/2021 $3.500 A 08/01/2022 $3.500 A 07/31/2023 $3.500 A
ROOFER 08/22/2018 07/31/2019** 08/01/2019 $2.000 H
ROOFER BITUMASTIC, ENAMELER, PIPE WRAPPER, COAL TAR PITCH BUILD-UP 08/22/2018 07/31/2019** 08/01/2019 $2.000 H
ROOFER MASTIC WORKER, KETTLEMAN 08/22/2018 07/31/2019** 08/01/2019 $2.000 H
SHEET METAL WORKER 08/22/2018 06/30/2019** 07/01/2019 $3.250 A 06/29/2020 $3.250 A 06/28/2021 $3.500 A
SHEET METAL WORKER TOTAL SHEET METAL CONTRACT OF $200000 OR LESS 02/22/2019 06/30/2019** 07/01/2019 $2.750 A 06/29/2020 $2.750 A 06/28/2021 $3.000 A
SHEET METAL WORKER SERVICE MECHANIC (TOTAL SHEET METAL CONTRACT OF $200000 OR LESS) 02/22/2019 06/30/2019** 07/01/2019 $1.950 A 06/29/2020 $1.950 A 06/28/2021 $2.100 A
SHEET METAL WORKER SERVICE TECHNICIAN (TOTAL SHEET METAL CONTRACT OF $200000 OR LESS) 08/22/2018 06/30/2019** 07/01/2019 $1.790 A 06/29/2020 $1.790 A 06/28/2021 $1.930 A
SHEET METAL WORKER AIR CONDITIONING SPECIALIST (TOTAL SHEET METAL CONTRACT OF $200000 OR LESS) 08/22/2018 06/30/2019** 07/01/2019 $1.460 A 06/29/2020 $1.460 A 06/28/2021 $1.580 A
SHEET METAL WORKER AIR CONDITIONING JOURNEYMAN (TOTAL SHEET METAL CONTRACT OF $200000 OR LESS) 08/22/2018 06/30/2019** 07/01/2019 $1.790 A 06/29/2020 $1.790 A 06/28/2021 $1.930 A

Return to wage page

FOOTNOTES

**
THE RATE TO BE PAID FOR WORK PERFORMED AFTER THIS DATE HAS BEEN DETERMINED. IF WORK WILL EXTEND PAST THIS DATE, THE NEW RATE MUST BE PAID AND SHOULD BE INCORPORATED IN CONTRACTS ENTERED INTO NOW. CONTACT THE OFFICE OF THE DIRECTOR RESEARCH UNIT FOR SPECIFIC RATES AT (415) 703-4774.
A
THE PREDETERMINED INCREASE SHOWN IS TO BE ALLOCATED TO WAGES AND/OR EMPLOYER PAYMENTS. PLEASE CONTACT THE OFFICE OF THE DIRECTOR - RESEARCH UNIT AT (415) 703-4774 WHEN THE PREDETERMINED INCREASE BECOMES DUE TO CONFIRM THE DISTRIBUTION. PLEASE ALSO EXAMINE THE IMPORTANT NOTICES TO SEE IF ANY MODIFICATIONS HAVE BEEN ISSUED, AS THERE MAY BE REDUCTIONS TO PREDETERMINED INCREASES.
B
ALL CREWS, WITHOUT CONSIDERATION TO THE NUMBER OF INDIVIDUALS IN THE CREW, SHALL INCLUDE A CHIEF OF PARTY. A CREW CONSISTS OF ONE (1) OR MORE EMPLOYEES PERFORMING FIELD AND CONSTRUCTION SURVEY WORK.
C
CERTIFIED MANIPULATOR WORK SHALL RECEIVE $1.25 PER HOUR ABOVE THE BASIC WAGE RATE
D
EMPLOYEES SHALL BE ENTITLED TO HIGH TIME PREMIUM WHENEVER THE WORK PERFORMED REQUIRES PERSONAL FALL RESTRAINTS TO BE WORN BY THE EMPLOYEE. THE AMOUNT OF THE PREMIUM SHALL BE AS FOLLOWS: AN ADDITIONAL $2.00 PER HOUR ABOVE BASIC HOURLY RATE WHEN WORKING OVER 50 FEET ABOVE GROUND OR WATER LEVEL, $4.00 PER HOUR WHEN WORKING FROM 100 TO 180 FEET AND $6.00 PER HOUR WHEN WORKING OVER 180 FEET. EMPLOYEES SHALL BE ENTITLED TO $2.00 PER HOUR ABOVE THE BASIC HOURLY RATE WHEN PERFORMING WORK FROM OR TO A SUSPENDED PLATFORM SUCH AS SAFESPAN, QUICKDECK OR COMPARABLE PLATFORM SYSTEMS ON BRIDGE AND OVERPASS TYPE WORK.
E
$1.00 TO BASIC HOURLY RATE AND $2.00 TO BE ALLOCATED TO WAGES AND/OR EMPLOYER PAYMENTS. PLEASE CONTACT THE OFFICE OF THE DIRECTOR - RESEARCH UNIT AT (415) 703-4774 WHEN THE PREDETERMINED INCREASE BECOMES DUE TO CONFIRM THE DISTRIBUTION. PLEASE ALSO EXAMINE THE IMPORTANT NOTICES TO SEE IF ANY MODIFICATIONS HAVE BEEN ISSUED, AS THERE MAY BE REDUCTIONS TO PREDETERMINED INCREASES.
F
EMPLOYEES SHALL BE ENTITLED TO HIGH TIME PREMIUM WHENEVER THE WORK PERFORMED REQUIRES PERSONAL FALL RESTRAINTS TO BE WORN BY THE EMPLOYEE. THE AMOUNT OF THE PREMIUM SHALL BE AS FOLLOWS: AN ADDITIONAL $4.00 PER HOUR WHEN WORKING FROM 100 TO 180 FEET ABOVE GROUND OR WATER LEVEL AND $6.00 PER HOUR WHEN WORKING OVER 180 FEET. EMPLOYEES SHALL BE ENTITLED TO $2.00 PER HOUR ABOVE THE BASIC HOURLY RATE WHEN PERFORMING WORK FROM OR TO A SUSPENDED PLATFORM SUCH AS SAFESPAN, QUICKDECK OR COMPARABLE PLATFORM SYSTEMS ON BRIDGE AND OVERPASS TYPE WORK.
G
$0.25 TO BASIC HOURLY RATE AND $2.00 TO BE ALLOCATED TO WAGES AND/OR EMPLOYER PAYMENTS. PLEASE CONTACT THE OFFICE OF THE DIRECTOR - RESEARCH UNIT AT (415) 703-4774 WHEN THE PREDETERMINED INCREASE BECOMES DUE TO CONFIRM THE DISTRIBUTION. PLEASE ALSO EXAMINE THE IMPORTANT NOTICES TO SEE IF ANY MODIFICATIONS HAVE BEEN ISSUED, AS THERE MAY BE REDUCTIONS TO PREDETERMINED INCREASES.
H
$0.55 TO H&W AND $1.45 TO BE ALLOCATED TO WAGES AND/OR EMPLOYER PAYMENTS. PLEASE CONTACT THE OFFICE OF THE DIRECTOR - RESEARCH UNIT AT (415) 703-4774 WHEN THE PREDETERMINED INCREASE BECOMES DUE TO CONFIRM THE DISTRIBUTION. PLEASE ALSO EXAMINE THE IMPORTANT NOTICES TO SEE IF ANY MODIFICATIONS HAVE BEEN ISSUED, AS THERE MAY BE REDUCTIONS TO PREDETERMINED INCREASES.

Return to main page