GENERAL PREVAILING WAGE DETERMINATION MADE BY THE DIRECTOR OF INDUSTRIAL RELATIONS PURSUANT TO CALIFORNIA LABOR CODE PART 7, CHAPTER 1, ARTICLE 2, SECTIONS 1770, 1773 AND 1773.1 FOR COMMERCIAL BUILDING, HIGHWAY, HEAVY CONSTRUCTION AND DREDGING PROJECTS

LOCALITY: SAN JOAQUIN COUNTY

DETERMINATION: SJO-2017-2

CRAFT CLASSIFICATION CRAFT FOOTNOTE ISSUE DATE EXPIRATION DATE DATE OF NEXT INCREASE 1 AMOUNT OF INCREASE 1 INCREASE FOOTNOTE 1 DATE OF NEXT INCREASE 2 AMOUNT OF INCREASE 2 INCREASE FOOTNOTE 2 DATE OF NEXT INCREASE 3 AMOUNT OF INCREASE 3 INCREASE FOOTNOTE 3 DATE OF NEXT INCREASE 4 AMOUNT OF INCREASE 4 INCREASE FOOTNOTE 4 DATE OF NEXT INCREASE 5 AMOUNT OF INCREASE 5 INCREASE FOOTNOTE 5
BRICKLAYER, BLOCKLAYER: BRICKLAYER, BLOCKLAYER, STONEMASON 08/22/2017 04/30/2018** 05/01/2018 $1.750 A
BRICK TENDER 08/22/2017 06/30/2018** 07/01/2018 $1.000 A 07/01/2019 $1.200 A
CARPET, LINOLEUM, RESILIENT TILE LAYER 02/22/2017 12/31/2017** 01/01/2018 $2.000 A
ELECTRICIAN: INSIDE WIREMAN, TECHNICIAN 08/22/2017 05/31/2018** 06/01/2018 $1.500 A 06/01/2019 $1.500 A
ELECTRICIAN: CABLE SPLICER-WELDER 08/22/2017 05/31/2018** 06/01/2018 $1.500 A 06/01/2019 $1.500 A
GLAZIER 02/22/2017 12/31/2017** 01/01/2018 $0.750 B
MARBLE FINISHER C 02/22/2017 07/31/2017** 08/01/2017 $1.850 A 08/01/2018 $2.200 A
MARBLE MASON C 02/22/2017 07/31/2017** 08/01/2017 $3.000 A 08/01/2018 $3.250 A
PAINTER: BRUSH, SPRAY, PAPERHANGER 08/22/2017 12/31/2017** 01/01/2018 $1.750 A 01/01/2019 $1.750 A 01/01/2020 $1.500 A
PAINTER: SANDBLASTER, STEAM CLEANER, WATERBLASTER 08/22/2017 12/31/2017** 01/01/2018 $1.750 A 01/01/2019 $1.750 A 01/01/2020 $1.500 A
PAINTER: EXOTIC MATERIALS 08/22/2017 12/31/2017** 01/01/2018 $1.750 A 01/01/2019 $1.750 A 01/01/2020 $1.500 A
PAINTER: TAPER 02/22/2017 12/31/2017** 01/01/2018 $2.050 D
PLASTERER 08/22/2017 12/31/2017** 01/01/2018 $0.980 A 07/01/2018 $3.730 A 01/01/2019 $0.980 A 07/01/2019 $3.730 A 07/01/2020 $2.750 A
PLASTER TENDER 08/22/2017 06/30/2018** 07/01/2018 $1.650 A
PLUMBER: PLUMBER, STEAMFITTER, REFRIGERATION FITTER (HVAC) 08/22/2017 12/31/2017** 01/01/2018 $1.250 A 07/01/2018 $1.250 A
PLUMBER: UNDERGROUND UTILITY PIPEFITTER 08/22/2017 06/30/2018** 07/01/2018 $1.500 E
PLUMBER: LANDSCAPE PIPEFITTER 08/22/2017 06/30/2018** 07/01/2018 $1.500 E
PLUMBER: UNDERGROUND UTILITY ASSISTANT JOURNEYMAN F 08/22/2017 06/30/2018** 07/01/2018 $1.500 E
PLUMBER: LANDSCAPE ASSISTANT JOURNEYMAN F 08/22/2017 06/30/2018** 07/01/2018 $1.500 E
PLUMBER: UNDERGROUND UTILITY TRADESMAN G 08/22/2017 06/30/2018** 07/01/2018 $1.900 H
PLUMBER: LANDSCAPE TRADESMAN I I 08/22/2017 06/30/2018** 07/01/2018 $1.900 H
PLUMBER: LANDSCAPE TRADESMAN II I 08/22/2017 06/30/2018** 07/01/2018 $1.900 H
PLUMBER: FIRE SPRINKLER FITTER (PROTECTION AND CONTROL SYSTEMS, OVERHEAD AND UNDERGROUND) 08/22/2017 12/31/2017** 01/01/2018 $0.700 J 04/01/2018 $1.950 K 01/01/2019 $0.550 L
ROOFER 08/22/2017 07/31/2018** 08/01/2018 $2.000 A
ROOFER BITUMASTIC, ENAMELER, COAL TAR, PITCH AND MASTIC WORKER 08/22/2017 07/31/2018** 08/01/2018 $2.000 A
TERRAZZO FINISHER M 08/22/2017 06/30/2018** 07/01/2018 $1.250 A
TERRAZZO WORKER M 08/22/2017 06/30/2018** 07/01/2018 $2.000 A
TILE FINISHER 08/22/2017 09/30/2017** 10/01/2017 N 04/01/2018 $2.040 A
TILE FINISHER RED CIRCLED FINISHER 08/22/2017 09/30/2017** 10/01/2017 $0.050 O 04/01/2018 $2.040 A
TILE SETTER 08/22/2017 09/30/2017** 10/01/2017 $0.350 P 04/01/2018 $3.400 A

Return to wage page

FOOTNOTES

**
THE RATE TO BE PAID FOR WORK PERFORMED AFTER THIS DATE HAS BEEN DETERMINED. IF WORK WILL EXTEND PAST THIS DATE, THE NEW RATE MUST BE PAID AND SHOULD BE INCORPORATED IN CONTRACTS ENTERED INTO NOW. CONTACT THE OFFICE OF THE DIRECTOR RESEARCH UNIT FOR SPECIFIC RATES AT (415) 703-4774.
A
THE PREDETERMINED INCREASE SHOWN IS TO BE ALLOCATED TO WAGES AND/OR EMPLOYER PAYMENTS. PLEASE CONTACT THE OFFICE OF THE DIRECTOR - RESEARCH UNIT AT (415) 703-4774 WHEN THE PREDETERMINED INCREASE BECOMES DUE TO CONFIRM THE DISTRIBUTION. PLEASE ALSO EXAMINE THE IMPORTANT NOTICES TO SEE IF ANY MODIFICATIONS HAVE BEEN ISSUED, AS THERE MAY BE REDUCTIONS TO PREDETERMINED INCREASES.
B
$0.75 TO PENSION.
C
EMPLOYEES WORKING ON ANY SUSPENDED PLATFORM/SCAFFFOLD SHALL BE PAID AN ADDITIONAL $20.00 PER DAY ABOVE THE WAGE RATE.
D
$0.48 TO PENSION AND $1.57 TO BE ALLOCATED TO WAGES AND/OR EMPLOYER PAYMENTS. PLEASE CONTACT THE OFFICE OF THE DIRECTOR - RESEARCH UNIT AT (415) 703-4774 WHEN THE PREDETERMINED INCREASE BECOMES DUE TO CONFIRM THE DISTRIBUTION. PLEASE ALSO EXAMINE THE IMPORTANT NOTICES TO SEE IF ANY MODIFICATIONS HAVE BEEN ISSUED, AS THERE MAY BE REDUCTIONS TO PREDETERMINED INCREASES.
E
$0.25 INCREASE TO BASIC HOURLY RATE, $1.00 TO HEALTH AND WELFARE AND $0.25 TO VACATION/HOLIDAY
F
THERE MUST BE AT LEAST ONE JOURNEYMAN PIPEFITTER PER CONTRACTOR ON EACH JOBSITE.
G
THERE SHALL BE NO MORE THAN THREE TRADESMEN TO EVERY TWO JOURNEYMAN PIPEFITTER/ASSISTANT JOURNEYMAN PIPEFITTER COMBINATION EMPLOYED PER CONTRACTOR ON EACH JOBSITE.
H
$0.65 INCREASE TO BASIC HOURLY RATE, $1.00 TO HEALTH AND WELFARE AND $0.25 TO VACATION/HOLIDAY
I
THERE SHALL BE NO MORE THAN FOUR TRADESMEN TO EVERY TWO JOURNEYMAN PIPEFITTER/ASSISTANT JOURNEYMAN PIPEFITTER COMBINATION EMPLOYED PER CONTRACTOR ON EACH JOBSITE. MAINTENANCE WORK, BOTH DURING AND AFTER THE PLANT ESTABLISHMENT PERIOD, MAY BE PERFORMED BY LANDSCAPE TRADESMEN WITHOUT THE SUPERVISION OF A JOURNEYMAN PIPEFITTER.
J
$0.50 TO HEALTH AND WELFARE AND $0.20 TO PENSION.
K
$1.65 TO THE BASIC HOURLY RATE, $0.25 TO PENSION AND $0.05 TO TRAINING.
L
$0.35 TO HEALTH AND WELFARE AND $0.20 TO PENSION.
M
THE RATIO OF TERRAZZO FINISHER HOURS TO TERRAZZO WORKER HOURS SHALL NOT EXCEED TWO (2) TO ONE (1).
N
INCREASE OF $0.40 TO BASIC HOURLY RATE AND $0.20 TO VACATION & HOLIDAY. DECREASE OF $0.60 TO OTHER.
O
INCREASE OF $0.59 TO BASIC HOURLY RATE, DECREASE OF $0.54 TO OTHER.
P
INCREASE OF $0.99 TO BASIC HOURLY RATE AND DECREASE OF $0.64 TO OTHER.