TITLE 8
GENERAL INDUSTRY SAFETY ORDERS, CHAPTER 4, SUBCHAPTER 7,
ARTICLE 6, SECTIONS 3292(d)(1) AND 3294(i)

EMERGENCY PROCEDURES PLAN FOR POWERED PLATFORMS
AND EQUIPMENT FOR BUILDING MAINTENANCE

Heard at the December 16, 1999, Public Hearing
Adopted on March 16, 2000
Approved by OAL on April 27, 2000
Effective May 27, 2000


Amend General Industry Safety Orders, Section 3292 to read:

§3292. General.

(a) Scope.
(1) This article covers powered platform installations permanently dedicated to interior or exterior building maintenance of a specific structure or group of structures. This article does not apply to suspended scaffolds used for construction work and covered under Article 23 of the Construction Safety Orders. Building maintenance includes, but is not limited to, such tasks as window cleaning, caulking, metal polishing and reglazing.
NOTE: It is recognized because of special site conditions that certain provisions contained in Article 5 may be applicable and can be used in conjunction with equipment and/or practices in this article.

* * * * *

(d)(1) Owners of buildings or structures shall develop an emergency procedures plan to assure both safe access to and egress from suspended permanent or transportable exterior and/or interior equipment. Where an Operating Procedures Outline Sheet (OPOS) has been developed for the building or structure in accordance with Appendix A of Article 5, the emergency procedures plan shall be incorporated into the OPOS.
(A) The emergency procedures plan shall be developed on a contract plan sheet in written and/or pictorial form and be available for review at the site by affected employees.
(B) Necessary features such as safety belt anchorages and adequate safe walkways required during emergencies shall be incorporated into the structure itself and delineated on the emergency procedure plan.
NOTE: Authority cited: Section 142.3, Labor Code. Reference: Section 142.3, Labor Code; and Section 18943(b), Health and Safety Code.

 

Amend General Industry Safety Orders, Section 3294 to read:

§3294. Powered Platform Installations - Affected Parts of Buildings.

* * * * *

(i) Emergency Planning. A written emergency action plan shall be developed and implemented for each kind of working platform operation in conjunction with the emergency procedures plan required of the building owner by Section 3292(d)(1). This plan shall explain the emergency procedures which are to be followed in the event of a power failure, equipment failure or other emergencies which may be encountered. The plan shall also explain that employees inform themselves about the building emergency escape routes, procedures and alarm systems before operating a platform. Upon initial assignment and whenever the plan is changed, the employer shall review with each employee those parts of the plan which the employee must know to protect himself or herself in the event of an emergency.

* * * * *

NOTE: Authority cited: Section 142.3, Labor Code. Reference: Section 142.3, Labor Code; and Section 18943(c), Health and Safety Code.