GENERAL PREVAILING WAGE DETERMINATION MADE BY THE DIRECTOR OF INDUSTRIAL RELATIONS PURSUANT TO CALIFORNIA LABOR CODE PART 7, CHAPTER 1, ARTICLE 2, SECTIONS 1770, 1773 AND 1773.1 FOR COMMERCIAL BUILDING, HIGHWAY, HEAVY CONSTRUCTION AND DREDGING PROJECTS
LOCALITY: SAN BENITO COUNTY
DETERMINATION: SBE-2026-1
PREDETERMINED INCREASES
| CRAFT | CLASSIFICATION | CRAFT FOOTNOTE | ISSUE DATE | EXPIRATION DATE | DATE OF NEXT INCREASE 1 | AMOUNT OF INCREASE 1 | INCREASE FOOTNOTE 1 | DATE OF NEXT INCREASE 2 | AMOUNT OF INCREASE 2 | INCREASE FOOTNOTE 2 | DATE OF NEXT INCREASE 3 | AMOUNT OF INCREASE 3 | INCREASE FOOTNOTE 3 | DATE OF NEXT INCREASE 4 | AMOUNT OF INCREASE 4 | INCREASE FOOTNOTE 4 | DATE OF NEXT INCREASE 5 | AMOUNT OF INCREASE 5 | INCREASE FOOTNOTE 5 | DATE OF NEXT INCREASE 6 | AMOUNT OF INCREASE 6 | INCREASE FOOTNOTE 6 | DATE OF NEXT INCREASE 7 | AMOUNT OF INCREASE 7 | INCREASE FOOTNOTE 7 | DATE OF NEXT INCREASE 8 | AMOUNT OF INCREASE 8 | INCREASE FOOTNOTE 8 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| BRICKLAYER, BLOCKLAYER: | BRICKLAYER, BLOCKLAYER, STONEMASON | 08/22/2025 | 04/30/2026** | 05/01/2026 | $3.250 | A | ||||||||||||||||||||||
| BRICK TENDER | 08/22/2025 | 06/30/2026** | 07/01/2026 | $3.710 | A | |||||||||||||||||||||||
| CARPET, LINOLEUM, | SOFT FLOOR LAYER | 02/22/2026 | 12/31/2026** | 01/01/2027 | $4.000 | A | ||||||||||||||||||||||
| ELECTRICIAN: | COMM & SYSTEM INSTALLER | 02/22/2026 | 11/30/2026** | 12/01/2026 | $4.250 | A | ||||||||||||||||||||||
| ELECTRICIAN: | COMM & SYSTEM TECH. | 02/22/2026 | 11/30/2026** | 12/01/2026 | $4.250 | A | ||||||||||||||||||||||
| ELECTRICIAN: | INSIDE WIREMAN, TECHNICIAN | 02/22/2026 | 12/27/2026** | 12/28/2026 | $4.700 | A | ||||||||||||||||||||||
| ELECTRICIAN: | CABLE SPLICER | 02/22/2026 | 12/27/2026** | 12/28/2026 | $4.700 | A | ||||||||||||||||||||||
| ELECTRICIAN: | INSIDE WIREMAN (WHEN WELDING) | 02/22/2026 | 12/27/2026** | 12/28/2026 | $4.700 | A | ||||||||||||||||||||||
| FIELD SURVEYOR: | CHIEF OF PARTY | B | 02/22/2026 | 02/28/2027** | 03/01/2027 | $5.000 | A | |||||||||||||||||||||
| FIELD SURVEYOR: | CHAINMAN/RODMAN | B | 02/22/2026 | 02/28/2027** | 03/01/2027 | $3.000 | A | |||||||||||||||||||||
| GLAZIER | C | 02/22/2026 | 12/31/2026** | 01/01/2027 | $4.500 | A | ||||||||||||||||||||||
| MARBLE FINISHER | D | 08/22/2025 | 07/31/2026** | 08/01/2026 | $2.500 | A | 08/01/2027 | $2.500 | A | 08/01/2028 | $2.750 | A | ||||||||||||||||
| MARBLE MASON | D | 08/22/2025 | 07/31/2026** | 08/01/2026 | $3.150 | A | 08/01/2027 | $3.250 | A | 08/01/2028 | $3.400 | A | ||||||||||||||||
| PLASTERER | 08/22/2025 | 06/30/2026** | 07/01/2026 | $4.000 | E | 07/01/2027 | $4.000 | E | 07/01/2028 | $4.000 | E | |||||||||||||||||
| PLUMBER: | PLUMBER, STEAMFITTER, REFRIGERATION FITTER (HVAC) | 08/22/2025 | 06/30/2026** | 07/01/2026 | $4.900 | A | ||||||||||||||||||||||
| PLUMBER: | SERVICE AND REPAIR | 08/22/2025 | 06/30/2026** | 07/01/2026 | $4.900 | A | ||||||||||||||||||||||
| PLUMBER: | FIRE SPRINKLER FITTER (PROTECTION AND CONTROL SYSTEMS, OVERHEAD AND UNDERGROUND) | 02/22/2026 | 03/31/2026** | 04/01/2026 | $3.030 | F | 01/01/2027 | $1.000 | G | 04/01/2027 | $3.040 | H | 01/01/2028 | $1.000 | G | 04/01/2028 | $0.500 | I | 01/01/2029 | $1.000 | G | 04/01/2029 | $0.500 | I | 01/01/2030 | $1.000 | G | |
| ROOFER | 08/22/2025 | 07/31/2026** | 08/01/2026 | $4.000 | A | |||||||||||||||||||||||
| ROOFER | BITUMASTIC, ENAMELER, PIPE WRAPPER, COAL TAR PITCH BUILD-UP | 08/22/2025 | 07/31/2026** | 08/01/2026 | $4.000 | A | ||||||||||||||||||||||
| ROOFER | MASTIC WORKER, KETTLEMAN | 08/22/2025 | 07/31/2026** | 08/01/2026 | $4.000 | A | ||||||||||||||||||||||
| SHEET METAL WORKER | ZONE 1 (UNDER 20 MILES) | J | 08/22/2025 | 06/30/2026** | 07/01/2026 | $4.000 | K | 07/01/2027 | $4.250 | L | 07/01/2028 | $4.500 | M | 07/01/2029 | $4.500 | N | ||||||||||||
| SHEET METAL WORKER | FOR SERVICE AND REPAIR | J | 08/22/2025 | 06/30/2026** | 07/01/2026 | $4.000 | K | 07/01/2027 | $4.250 | L | 07/01/2028 | $4.500 | M | 07/01/2029 | $4.500 | N | ||||||||||||
| TERRAZZO FINISHER | O | 08/22/2025 | 06/30/2026** | 07/01/2026 | $2.500 | A | ||||||||||||||||||||||
| TERRAZZO WORKER | O | 08/22/2025 | 06/30/2026** | 07/01/2026 | $3.000 | A | ||||||||||||||||||||||
| TILE SETTER | 08/22/2025 | 03/31/2026** | 04/01/2026 | $3.000 | A | 04/01/2027 | $3.500 | A | ||||||||||||||||||||
| WATER WELL DRILLER: | 08/22/2025 | 06/30/2026** | 07/01/2026 | $2.000 | A | |||||||||||||||||||||||
| WATER WELL DRILLER: | PUMP INSTALLER | 08/22/2025 | 06/30/2026** | 07/01/2026 | $2.000 | A | ||||||||||||||||||||||
| WATER WELL DRILLER: | HELPER | 08/22/2025 | 06/30/2026** | 07/01/2026 | $2.000 | A |
FOOTNOTES
- **
- THE RATE TO BE PAID FOR WORK PERFORMED AFTER THIS DATE HAS BEEN DETERMINED. IF WORK WILL EXTEND PAST THIS DATE, THE NEW RATE MUST BE PAID AND SHOULD BE INCORPORATED IN CONTRACTS ENTERED INTO NOW. CONTACT THE OFFICE OF THE DIRECTOR RESEARCH UNIT FOR SPECIFIC RATES AT (415) 703-4774.
- A
- THE PREDETERMINED INCREASE SHOWN IS TO BE ALLOCATED TO WAGES AND/OR EMPLOYER PAYMENTS. PLEASE CONTACT THE OFFICE OF THE DIRECTOR - RESEARCH UNIT AT (415) 703-4774 WHEN THE PREDETERMINED INCREASE BECOMES DUE TO CONFIRM THE DISTRIBUTION. PLEASE ALSO EXAMINE THE IMPORTANT NOTICES TO SEE IF ANY MODIFICATIONS HAVE BEEN ISSUED, AS THERE MAY BE REDUCTIONS TO PREDETERMINED INCREASES.
- B
- ALL CREWS, WITHOUT CONSIDERATION TO THE NUMBER OF INDIVIDUALS IN THE CREW, SHALL INCLUDE A CHIEF OF PARTY. A CREW CONSISTS OF ONE (1) OR MORE EMPLOYEES PERFORMING FIELD AND CONSTRUCTION SURVEY WORK.
- C
- CERTIFIED MANIPULATOR WORK SHALL RECEIVE $2.00 PER HOUR ABOVE THE BASIC WAGE RATE
- D
- EMPLOYEES WORKING ON ANY SUSPENDED PLATFORM/SWING STAGE SHALL BE PAID AN ADDITIONAL $20.00 PER DAY ABOVE THE WAGE RATE.
- E
- $0.25 TO HEALTH&WELFARE, $0.50 TO PENSION, AND $3.25 TO BE ALLOCATED TO WAGES AND/OR EMPLOYER PAYMENTS.
- F
- $3.03 TO BASIC HOURLY RATE.
- G
- $0.95 TO HEALTH AND WELFARE, AND $0.05 TO PENSION.
- H
- $3.04 TO BASIC HOURLY RATE.
- I
- $0.50 TO PENSION.
- J
- APPLIES TO JOBSITES UNDER 20 MILES FROM MARKET AND MAIN STREETS IN SALINAS, CA (MONTEREY COUNTY) AND 5TH AND SAN BENITO STREETS IN HOLLISTER, CA (SAN BENITO COUNTY). FOR RATES OUTSIDE THESE ZONES REFER TO THE TRAVEL AND SUBSISTENCE PROVISIONS APPLICABLE TO THIS DETERMINATION.
- K
- $0.15 TO OTHER, $0.02 TO HEALTH & WELFARE AND $3.83 TO WAGES AND/OR FRINGES.
- L
- $0.10 TO OTHER, $0.01 TO TRAINING AND $4.14 TO WAGES AND/OR FRINGES.
- M
- $0.05 TO OTHER AND $4.45 TO WAGES AND/OR FRINGES.
- N
- $0.05 TO OTHER AND $4.45 TO WAGES AND/OR FRINGES.
- O
- THE RATIO OF TERRAZZO FINISHER HOURS TO TERRAZZO WORKER HOURS SHALL NOT EXCEED TWO (2) TO ONE (1).